The monthly CC Status Summary
Spreadsheet shows the prioritized project list, our initial estimated cost of each project, actual
contractor quotes we have received for the work and much more.
This is the first CC’22 Status Summary since October 2024. We have had difficulty with the Air
Conditioning (AC) project. We lost the mechanical engineer we were originally working with, but
found a new one who has been working with us since October 2024. The AC project is the
largest cost project in the CC. As mentioned at the Mid-year congregational meeting in
January, we have been wary of moving forward with too many other projects until we have a
handle on the AC cost, hence there has been reduced spending of CC funds recently.
Please click this link to review the latest CC Status Summary Spreadsheet update.
We are still working on several projects other than the AC. Projects with signed contracts
include, the Memorial Walls in the Celebration Garden, Stormwater Improvements, additional
Solar Panels and the Mechanical Engineer for design of the AC system.
See this link for a more detailed discussion of our progress to date.
We are trying to self-perform as much of the work as possible. Anyone with a desire to lend a
hand is welcome to contact Joe Meier (see below). People with electrical wiring or carpentry
skills would be especially welcome. Any questions or offers of help can be sent to Joe Meier at [email protected]